
Working hard in this bipolar Vancouver weather. Here is a compiled list of construction updates for Harrison Ridge Development.

TOWNHOMES
PHASE ONE
Building 7 (UNIT 1-4): Working full long hours in the heavy rain this month, our handy construction workers have finished completion of the framing, and rough in’s of plumbing and electrical has been installed. Now we are ready for installation next week for exterior finishings.
Rough est. completion date: Despite all the challenges we faced due to COVID-19, we target to complete the first phase by Jan 2023.
PHASE TWO
Building 1 (UNIT 61-64):
Lots of progress for Building 1. We have completed the first-floor framing and just finishing up the second-floor framing. Overall we are looking to compete framing next week. After completion of framing, they will move on to framing Building 2.
Rough est. completion date: Feb 2023

Building 2 (UNIT 57-60):
Foundation and concrete have been poured for Building 2. We are waiting for the concrete to be completed this week for the first floor. After drying on concrete on the first floor framing will go up for the respectful floor then we will move up to the second-floor concrete and framing.
Rough est. completion date: March 2023

Playground

We are planning on opening the playground up for the public by next spring.
Asphalt
Has been poured on roads.
